Procurement Process (OS&E).
To be adapted to the needs of the project.

Phase 1   Kickoff  (by Robert/Client)

The procurement process begins with a review of the project brief. I then prepare a preliminary proposal.

images (1)

Phase 2  Agree Contract.

Contract to be agreed with Client.

Scope of OS&E.

Order batches and time.

shaking-hands-3641642__340

Phase 3  Product standards, master-lists, budgets, BOQs.. (By Robert)

This stage requires input from the hotel, the operator, Client and  the designer.

Phase 4 Competitive tender process.  By Client.

Selection of suppliers and products is normally through competitive tendering (normally 2-3 per main bid package)

Phase 5  Orders.

 Purchase order and payments(by Client).

ORDER

Phase 6 Logistics

Pre-shipment inspection. (by Robert for EU/UK and or third party inspector)

Logistics. (by Client) who appoints  freight forwarder whose services includes:

Phase 7 (G) Import/Clear goods;  Receipt of Goods (coordinated by Client’s local team)  through freight forwarder/local customs broker 

Installation (by Client’s local team/Hotel).  

It is essential that a strict control be exercised on the delivery of material to the project.

Phase 8   Finalisation process. (by Client’s local team)

This  stage is required to verify quality and ensure that the procurement process is completed  and any issues  satisfactorily resolved.