Master-lists Room Service
Room service Comments
- Confirm quantity of shoe polishers – Confirm with hotel and PM
- Confirm finish of shoe polishers – Confirm with Designer
- Ensure that there is power supplied – Confirm with Project Manager
- Ice machines not normally OS&E – Confirm with Project Manager, kitchen contractor
- Ice machines require power and drainage supplied, are in accordance with architects plans – Confirm with Project Manager
- Confirm finish and dimensions of ice machines? Are they recessed in wall? – Confirm with Project Manager/Designer
- Make sure the room service trays fit the corridor tray trolley – Check with supplier
- Are room service trolleys in OS&E or kitchen contract? – Crosscheck kitchen contract
- Buyer to confirm that the trolleys fits in service lifts, and all doorways – Check with supplier /Project Manager
- Appropriate castors are required depending on floor surfaces eg carpet or marble (ie marble is slippy) – Check with supplier /Project Manager
- Box stand to hold food warmers .Electrical power connections required . Installation co-ordinated with Project Manager. – Coordinate with Project Manager